ABU DHABI MUNICIPALITY DATA CENTER (TIER III)

Corporate Finance and their Revenue in Major Areas

Managing the implementation of a TIER 3 Data Center project, the solution included the following systems:

  1. Construction of the Data center building.
  2. Fire detection and suppression systems.
  3. Intelligent Closed circuit cooling system (Smart Aisle CCU).
  4. UPS System.
  5. Backup generator.
  6. Busbar electrical distribution.
  7. Intelligent power distribution boards units.

The was to manage the following:

  1. Managing Design cycle.
  2. Managing the Authorities approval for utilities and other services.
  3. Managing the supply chain.
  4. Vendors management.
  5. Implementation management.
  6. Change and risk management.
  7. Commissioning and testing management.
  8. Placing the project in operation.